[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927052":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},927052,598,1,"单选题","在施工缝处继续浇筑混凝土时，应待已浇筑的混凝土强度不低于（ ）时才允许继续浇筑。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1.2N\u002Fmm2",true,{"key":16,"text":17,"correct":18},"B","2.0N\u002Fmm2",false,{"key":20,"text":21,"correct":18},"C","75%的强度标准值",{"key":23,"text":24,"correct":18},"D","90%的强度标准值","在施工缝处继续浇筑混凝土时，应符合下列规定：①已浇筑的混凝土，抗压强度不应小于1.2N\u002Fmm2；②清除水泥薄膜和松动石子以及软弱混凝土层，并加以充分湿润和冲洗干净，且不得积水；③在浇筑混凝土前，宜先在施工缝处刷一层水泥浆（可掺适量界面剂）或铺一层与混凝土内成分相同的水泥砂浆；④混凝土应细致捣实，使新旧混凝土紧密结合。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]