[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927051":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},927051,598,1,"单选题","当有主次梁楼盖的混凝土不能连续浇筑时，施工缝应留在（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","主梁跨中1\u002F3范围内",false,{"key":16,"text":17,"correct":18},"B","次梁跨中1\u002F3范围内",true,{"key":20,"text":21,"correct":14},"C","主梁跨边1\u002F3范围内",{"key":23,"text":24,"correct":14},"D","次梁跨边1\u002F3范围内","施工缝的位置应设置在结构受剪力较小和便于施工的部位，且应符合下列规定：①施工缝应留置在基础的顶面、梁或吊车梁牛腿的下面、吊车梁的上面、无梁楼板柱帽的下面；②和楼板连成整体的大断面梁，施工缝应留置在板底面以下20mm～30mm处，当板下有梁托时，留置在梁托下部；③对于单向板，施工缝应留置在平行于板的短边的任何位置；④有主次梁的楼板，宜顺着次梁方向浇筑，施工缝应留置在次梁跨度中间1\u002F3的范围内；⑤墙上的施工缝应留置在门洞口过梁跨中1\u002F3范围内，也可留在纵横墙的交接处；⑥楼梯上的施工缝应留在踏步板的1\u002F3处；⑦水池池壁的施工缝宜留在高出底板表面200mm～500mm的竖壁上；⑧双向受力楼板、大体积混凝土、拱、壳、仓、设备基础、多层刚架及其他复杂结构，施工缝位置应按设计要求留设；⑨柱应留水平缝，梁、板、墙应留垂直缝。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]