[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927025":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},927025,598,1,"单选题","深度达18m的基础工程，在条件适宜的情况下，基坑支护型式可选择（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","水泥土墙",false,{"key":16,"text":17,"correct":18},"B","地下连续墙",true,{"key":20,"text":21,"correct":14},"C","土钉墙",{"key":23,"text":24,"correct":14},"D","逆作拱墙","常见的基坑支护型式主要有：①排桩支护；②桩撑、桩锚、排桩悬臂；③地下连续墙支护，地连墙+支撑；水泥挡土墙；④钢板桩：型钢桩横挡板支护，钢板桩支护；⑤土钉墙（喷锚支护）；⑥逆作拱墙；⑦原状土放坡；⑧基坑内支撑；⑨桩、墙加支撑系统；⑩简单水平支撑；钢筋混凝土排桩；上述两种或者两种以上方式的合理组合等。地下连续墙整体刚度大、抗渗性好、对环境影响小，适用于基坑深度大、地质环境复杂、周围环境要求高的情况。18m属于深基坑，应采用地下连续墙。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]