[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927019":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},927019,598,1,"单选题","隐蔽工程在隐蔽以前，承包人应当通知发包人检查。发包人没有及时检查的，承包人可以（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","顺延工程日期，并有权要求赔偿停工、窝工等损失",true,{"key":16,"text":17,"correct":18},"B","顺延工程日期，但应放弃其他要求",false,{"key":20,"text":21,"correct":18},"C","发包人默认隐蔽工程质量，可继续施工",{"key":23,"text":24,"correct":18},"D","工期不变，建设单位承担停工、窝工等损失","《合同法》第二百七十八条规定，隐蔽工程在隐蔽以前，承包人应当通知发包人检查。发包人没有及时检查的，承包人可以顺延工程日期，并有权要求赔偿停工、窝工等损失。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]