[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927002":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},927002,598,1,"单选题","某建设项目进行环境影响评价过程中，涉及水土保持问题，则该评价中还必须有（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","经环境保护主管部门同意的水土保持方案",false,{"key":16,"text":17,"correct":14},"B","经土地主管部门同意的水土保持方案",{"key":19,"text":20,"correct":21},"C","经水行政主管部门审查同意的水土保持方案",true,{"key":23,"text":24,"correct":14},"D","经建设主管部门同意的水土保持方案","根据《环境影响评价法》第十七条的规定，涉及水土保持的建设项目，必须有经水行政主管部门审查同意的水土保持方案。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]