[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-926975":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},926975,598,1,"单选题","某工程项目自环境影响报告书批准之日起一直没有建设，需要对该文件进行重新审核的年限是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2年",false,{"key":16,"text":17,"correct":14},"B","3年",{"key":19,"text":20,"correct":21},"C","5年",true,{"key":23,"text":24,"correct":14},"D","7年","环境影响报告书、环境影响报告表或者环境影响登记表自批准之日起满五年，建设项目方开工建设的，其环境影响报告书、环境影响报告表或者环境影响登记表应当报原审批机关重新审核。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]