[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-926590":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},926590,598,1,"单选题","在钢筋混凝土连续梁活荷载的不利布置中，若求支座的最大剪力，则下列对活荷载布置方法的叙述中哪个是正确的？",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","在该支座的左跨布置活荷载，并隔跨布置",false,{"key":16,"text":17,"correct":14},"B","在该支座的右跨布置活荷载，并隔跨布置",{"key":19,"text":20,"correct":21},"C","在该支座的相邻两跨布置活荷载，并隔跨布置",true,{"key":23,"text":24,"correct":14},"D","所有跨布置活荷载","",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]