[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-926358":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},926358,598,1,"单选题","在网络计划中，下列中哪项为零，则该工作必为关键工作？",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","自由时差",false,{"key":16,"text":17,"correct":18},"B","总时差",true,{"key":20,"text":21,"correct":14},"C","时间间隔",{"key":23,"text":24,"correct":14},"D","工作持续时间","提示：网络计划时间参数计算中，总时差为零的工作必在关键线路上，则必为关键工作。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]