[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-926353":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},926353,598,1,"单选题","双代号网络图的三要素是：",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","时差、最早时间和最迟时间",false,{"key":16,"text":17,"correct":14},"B","总时差、局部时差和计算工期",{"key":19,"text":20,"correct":21},"C","工作、事件和线路",true,{"key":23,"text":24,"correct":14},"D","工作、事件和关键线路","提示：工作、事件组成了基本网络图形，由原始事件到结束事件又形成了多条线路，诸条线路中可找出一条关键线路。故线路、工作、事件是网络图的最基本要素。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]