[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-926352":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},926352,598,1,"单选题","单代号网络图中，某工作最早完成时间与其紧后工作的最早开始时间之差为：",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总时差",false,{"key":16,"text":17,"correct":18},"B","自由时差",true,{"key":20,"text":21,"correct":14},"C","虚工作",{"key":23,"text":24,"correct":14},"D","时间间隔","提示：自由时差的概念是紧后工作的最早开始时间减去本工作的最早完成时间的差值。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]