[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-926350":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},926350,598,1,"单选题","某流水施工组织成加快成倍节拍流水，施工段数为6，甲、乙、丙三个施工过程的流水节拍分别为1d、2d和3d，其流水工期为：",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","8d",false,{"key":16,"text":17,"correct":14},"B","10d",{"key":19,"text":20,"correct":21},"C","11d",true,{"key":23,"text":24,"correct":14},"D","16d","提示：加快成倍节拍流水工期计算公式：流水工期= (m+N-1)K0=(6 + 6-1)X1=11d。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]