[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-926344":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},926344,598,1,"单选题","对有技术间歇的分层分段流水施工，最少施工段数与施工过程数相比，应：",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","小于",false,{"key":16,"text":17,"correct":14},"B","等于",{"key":19,"text":20,"correct":21},"C","大于",true,{"key":23,"text":24,"correct":14},"D","小于、等于","提示：对有技术间歇的分层分段流水施工，最少施工段数应大于施工过程数。必须为技术间歇留出适当空间，否则，会造成窝工。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]