[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-926303":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},926303,598,1,"单选题","关于先张法预应力混凝土施工，下列中哪个规定是正确的？",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","混凝土强度不得低于C15",false,{"key":16,"text":17,"correct":18},"B","混凝土必须一次浇灌完成",true,{"key":20,"text":21,"correct":14},"C","混凝土强度达到50%方可放张",{"key":23,"text":24,"correct":14},"D","不可成组张拉","提示：先张法预应力混凝土施工中，对混凝土强度要求不低于C25，混凝土强度达到75%方可放张，预应力钢筋可成组张拉，混凝土必须一次浇灌完成。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]