[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-926298":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},926298,598,1,"单选题","后张法施工时，浇筑构件混凝土的同时先预留孔道，待构件混凝土的强度达到设计强度等级的多少后，方可张拉钢筋？",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","50%",false,{"key":16,"text":17,"correct":14},"B","60%",{"key":19,"text":20,"correct":21},"C","75%",true,{"key":23,"text":24,"correct":14},"D","80%","提示：根据《混凝土结构工程施工质量验收规范》(GB 50204-2002)中第6. 4. 1条的规定，预应力筋张拉时，结构的混凝土强度应符合设计要求；当设计无具体要求时，不应低于设计强度标准值的75%。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]