[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-926283":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},926283,598,1,"单选题","用作预应力筋的钢筋冷拉时，应采用的方法是：",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","控制冷拉率法",false,{"key":16,"text":17,"correct":18},"B","双控法",true,{"key":20,"text":21,"correct":14},"C","单控法",{"key":23,"text":24,"correct":14},"D","无须控制","提示：钢筋冷拉的控制方法有两种:一种是控制冷拉率法，另一种是双控制法。采用控制冷拉率法时，只要伸长值达到，即认为合格。此法较简单，但钢筋材质不均时，不能真正反映冷拉程度，只能用作非预应力筋的冷拉。预应力筋必须保证足够的强度，因此必须采用双控制方法，即由冷拉率和冷拉应力两方面控制。这样才能保证钢筋冷拉后的强度符合要求，且冷拉率又不超过最大冷拉率。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]