[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-926264":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},926264,598,1,"单选题","拟测设距离D=49. 550m，两点间坡度均匀，高差为1.686m，丈量时的温度为27° C，所用的钢尺的尺长方程式为lt=30m+0. 004m+0. 0000125(t-20) X 30m，则测设时在地面上应量多少？",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","49. 546m",false,{"key":16,"text":17,"correct":14},"B","49. 571m",{"key":19,"text":20,"correct":14},"C","49. 531m",{"key":22,"text":23,"correct":24},"D","49. 568m",true,"提示：30m钢尺的实际长度:lt=30+0. 004m+0. 0000125(27-20) X 30m= 30. 007m ；地面上的应丈量距离为： 地面上的钢尺量距读数为：S尺=",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]