[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-923837":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},923837,597,1,"单选题","对某项目投资方案进行单因素敏感性分析，基准收益率15%，采用内部收益率作为评价指标，投资额、经营成本、销售收入为不确定性因素，计算其变化对IRR的影响如表所示。则敏感性因素按对评价指标影响的程度从大到小排列依次为：",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投资额、经营成本、销售收入",false,{"key":16,"text":17,"correct":18},"B","销售收入、经营成本、投资额",true,{"key":20,"text":21,"correct":14},"C","经营成本、投资额、销售收入",{"key":23,"text":24,"correct":14},"D","销售收入、投资额、经营成本","提示：变化幅度的绝对值相同时(如变化幅度为±20%)，敏感性系数较大者对应的因素较敏感。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 基础考试一级","建筑工程",0]