[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-923826":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},923826,597,1,"单选题","从经济资源配置的角度判断建设项目可以被接受的条件是：",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","财务净现值等于或大于零",false,{"key":16,"text":17,"correct":14},"B","经济内部收益率等于或小于社会折现率",{"key":19,"text":20,"correct":14},"C","财务内部收益率等于或大于基准收益率",{"key":22,"text":23,"correct":24},"D","经济净现值等于或大于零",true,"提示：经济净现值等于或大于零，表明项目的经济盈利性达到或超过了社会折现率的基本要求。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 基础考试一级","建筑工程",0]