[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-923097":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},923097,596,1,"单选题","可行性研究阶段的主要任务是对拟建项目的技术经济、工程建设等内容进行多方案比较，从而进行( )工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制设计任务书",false,{"key":16,"text":17,"correct":18},"B","决定是否投资和如何投资该项目",true,{"key":20,"text":21,"correct":14},"C","推荐最佳设计单位",{"key":23,"text":24,"correct":14},"D","选择承包商","可行性研究的主要任务，是按照国民经济长期规划的地区规划、行业规划的要求，对拟建项目进行投资方案规划、工程技术论证、社会与经济效果预测和组织机构分析，经过多方面的计算、分析、论证评价，为项目决策者提供可靠的依据和建议。项目投资决策者主要根据可行性研究的评价结果，决定一个建设项目是否应该投资和如何投资。",{"id":6,"name":27,"category":28,"favorite":29},"设计前期与场地设计","建筑工程",0]