[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-923034":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},923034,596,1,"单选题","当场地勘察资料缺乏、建筑平面位置未定或场地面积较大且为高层建筑群时，勘察分为以下何阶段进行？( )",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","可行性研究、初步勘察、详细勘察三阶段",false,{"key":16,"text":17,"correct":14},"B","参考周边勘察资料和详细勘察两阶段",{"key":19,"text":20,"correct":21},"C","初步勘察和详细勘察两阶段",true,{"key":23,"text":24,"correct":14},"D","合并为详细勘察一阶段","《高层建筑岩土工程勘察规程》3.0.2勘察阶段的划分宜符合下列规定：(1)对城市中重点的勘察等级为甲级的高层建筑，勘察阶段宜分为可行性研究、初步勘察、详细勘察三阶段进行。(2)当场地勘察资料缺乏、建筑平面位置未定，或场地面积较大、为高层建筑群时，勘察阶段宜分为初步勘察和详细勘察两阶段进行。(3)当场地及其附近已有一定勘察资料，或勘察等级为乙级的单体建筑且建筑总平面图已定时，可将两阶段合并为一阶段，按详细勘察阶段进行。(4)对于一级(复杂)场地或一级(复杂)地基的工程，可针对施工中可能出现或已出现的岩土工程问题，进行施工勘察。地基基础施工时，勘察单位宜参与施工验槽。",{"id":6,"name":27,"category":28,"favorite":29},"设计前期与场地设计","建筑工程",0]