[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-923030":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},923030,596,1,"单选题","某外商拟在—开发区投资建厂，该项目已立项，接下来应进行( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","委托设计单位进行设计",false,{"key":16,"text":17,"correct":14},"B","合营双方签约",{"key":19,"text":20,"correct":14},"C","招收新职员进行技术培训",{"key":22,"text":23,"correct":24},"D","编制可行性研究报告",true,"根据外商投资项目建设程序：①项目建议书；②可行性研究报告；③对外签约；④批准证书；⑤申请登记等设计前期工作内容。项目建议书经主管部门审批通过，正式获得批准立项，方可进入可行性研究报告的工作阶段。",{"id":6,"name":27,"category":28,"favorite":29},"设计前期与场地设计","建筑工程",0]