[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-923025":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},923025,596,1,"单选题","下列哪个日期是建设项目的竣工日期？( )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建筑施工完成日期",false,{"key":16,"text":17,"correct":14},"B","设备安装完成日期",{"key":19,"text":20,"correct":14},"C","设备运转试生产日期",{"key":22,"text":23,"correct":24},"D","有关验收单位或验收组验收合格的日期",true,"《关于审理建设工程施工合同纠纷案件适用法律问题的解释》第14条规定，当事人对建设工程实际竣工日期有争议的，按照以下情形分别处理：(一)建设工程经竣工验收合格的，以竣工验收合格之日为竣工日期；(二)承包人已经提交竣工验收报告，发包人拖延验收的，以承包人提交验收报告之日为竣工日期；(三)建设工程未经竣工验收，发包人擅自使用的，以转移占有建设工程之日为竣工日期。",{"id":6,"name":27,"category":28,"favorite":29},"设计前期与场地设计","建筑工程",0]