[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-923006":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},923006,596,1,"单选题","下列哪项不属于新建设项目的设计前期工作？( )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","有关的国土规划、区域规划、地市规划、专业规划的基础资料",false,{"key":16,"text":17,"correct":14},"B","编制项目建议书",{"key":19,"text":20,"correct":14},"C","收集地质、水文、气象、地震等资料",{"key":22,"text":23,"correct":24},"D","编制建设项目总预算",true,"A项属于项目建议书阶段内容、C项属于可行性研究内容，均属于设计前期工作。新建设项目的设计前期工作不包括编制项目总预算。",{"id":6,"name":27,"category":28,"favorite":29},"设计前期与场地设计","建筑工程",0]