[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-923002":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},923002,596,1,"单选题","下列哪个是施工建设阶段的开始日期？( )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","开始拆除原有建筑物动工之日",false,{"key":16,"text":17,"correct":14},"B","三通一平开始动工之日",{"key":19,"text":20,"correct":14},"C","地质详勘开始进场之日",{"key":22,"text":23,"correct":24},"D","建设项目第一次正式破土开槽动工之日",true,"工程项目经批准开工建设，项目即进入了施工阶段。项目开工时间，是指工程建设项目设计文件中规定的任何一项永久性工程第一次正式破土开槽开始施工的日期。不需开槽的工程，正式开始打桩的日期就是开工日期。",{"id":6,"name":27,"category":28,"favorite":29},"设计前期与场地设计","建筑工程",0]