[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-922938":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},922938,596,1,"单选题","为预防洪水侵袭，下列措施中哪项是不适宜的？( )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在坡地建筑物的高坡一侧布设截洪沟",false,{"key":16,"text":17,"correct":14},"B","场址不应选在紧靠水坝坝址的下游一侧",{"key":19,"text":20,"correct":14},"C","场址不应选择在经常泛滥的江湖两侧，特别在洪水淹没线的范围以内",{"key":22,"text":23,"correct":24},"D","设计建筑物和构筑物的地坪标高，应高出计算洪水水位0.30m",true,"《全国民用建筑工程设计技术措施规划·建筑》(2009年)第3.1.3条规定，场地设计标高应高于或等于城市设计防洪、防涝标高；沿海或受洪水泛滥威胁地区，场地设计标高应高于设计洪水位标高0.5～1.0m，否则必须采取相应的防洪措施。",{"id":6,"name":27,"category":28,"favorite":29},"设计前期与场地设计","建筑工程",0]