[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-922925":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},922925,596,1,"单选题","在实施投资估算中，下列哪项不能满足控制投资的需要？( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设项目建议书和可行性研究",true,{"key":16,"text":17,"correct":18},"B","工程设计招标、投标或方案设计",false,{"key":20,"text":21,"correct":18},"C","限额设计",{"key":23,"text":24,"correct":18},"D","施工费用","可行性研究中的投资估算是进行设计招标、优选设计单位和设计方案、实行限额设计以及施工费用的依据。",{"id":6,"name":27,"category":28,"favorite":29},"设计前期与场地设计","建筑工程",0]