[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-922889":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},922889,596,1,"单选题","甲方要求加快某大型公建工程进度，采用以下的方法中哪种是不合适的？( )",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","增加设计力量，压缩设计周期",false,{"key":16,"text":17,"correct":14},"B","两班倒，冬期施工，加快施工进度",{"key":19,"text":20,"correct":21},"C","省却初步设计阶段，方案批准后，立即做施工图设计",true,{"key":23,"text":24,"correct":14},"D","实行平行流水作业，多工种交叉施工","《关于加强大型公共建筑工程建设管理的若干意见》规定：鼓励对大型公共建筑工程的初步设计进行优化设计，提高投资效益。",{"id":6,"name":27,"category":28,"favorite":29},"设计前期与场地设计","建筑工程",0]