[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-922835":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},922835,596,1,"单选题","根据基本建设程序，在投资建设项目之前，首先应做的工作是以下( )项。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进行实地考察，确定建设地点，做征地拆迁的准备工作",false,{"key":16,"text":17,"correct":18},"B","提出项目建议书",true,{"key":20,"text":21,"correct":14},"C","进行投资估算和资金筹措",{"key":23,"text":24,"correct":14},"D","对项目进行初步设计","我国现行的基本建设程序包括的主要阶段依次有：①项目建议书阶段；②可行性研究阶段；③设计工作阶段；④建设准备阶段；⑤建设实施阶段；⑥生产准备阶段；⑦竣工验收阶段。",{"id":6,"name":27,"category":28,"favorite":29},"设计前期与场地设计","建筑工程",0]