[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-922829":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},922829,596,1,"单选题","在选址阶段，可暂不收集下列何种基础资料？( )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","气象、水文、地貌、地质、自然灾害资料",false,{"key":16,"text":17,"correct":14},"B","生态环境资料",{"key":19,"text":20,"correct":14},"C","市政、公用工程设施资料",{"key":22,"text":23,"correct":24},"D","各类建筑工程造价资料",true,"根据《建筑设计资料集·5》，“厂址选择”部分“基础资料收集提纲”中要求收集的资料包括：①气象、水文、地貌、地质、自然灾害资料；②生态环境资料；③市政、公用工程设施资料。各类建筑工程造价资料在项目选址阶段还没开始考虑，因此项目选址与各类建筑工程造价资料无关。",{"id":6,"name":27,"category":28,"favorite":29},"设计前期与场地设计","建筑工程",0]