[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-922820":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},922820,596,1,"单选题","下列哪条不属于项目建议书内有关环保的主要内容？( )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","所在地区环境现状",false,{"key":16,"text":17,"correct":14},"B","建成后可能造成的环境影响分析",{"key":19,"text":20,"correct":14},"C","当地环保部门的意见和要求",{"key":22,"text":23,"correct":24},"D","当地交通部门的意见和要求",true,"项目建议书阶段：项目建议书中应根据建设项目的性质、规模、建设地区的环境现状等有关资料，对建设项目建成投产后可能造成的环境影响进行简要说明，其主要内容如下：①所在地区的环境现状；②可能造成的环境影响分析；③当地环保部门的意见和要求；④存在的问题。交通部门要求的车辆数，与环保要求无关。",{"id":6,"name":27,"category":28,"favorite":29},"设计前期与场地设计","建筑工程",0]