[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-922801":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},922801,596,1,"单选题","建设项目的环境影响报告书(或表)，应当在( )阶段完成。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目建议书",false,{"key":16,"text":17,"correct":14},"B","初步可行性研究",{"key":19,"text":20,"correct":21},"C","可行性研究",true,{"key":23,"text":24,"correct":14},"D","初步设计","可行性研究阶段的内容：项目建设的必要性、市场分析、项目建设方案研究、投资估算、融资方案、财务分析、经济分析、经济影响分析、资源利用分析、土地利用及移民搬迁安置方案分析、社会评价、不确定性分析，风险分析。其中社会评价就包含了环境影响分析，建设项目的可行性研究报告必须有环境保护篇(章)具体落实环境影响报告书(或表)。",{"id":6,"name":27,"category":28,"favorite":29},"设计前期与场地设计","建筑工程",0]