[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-922622":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},922622,596,1,"单选题","工程管线平面位置和竖向位置应采用的坐标系统和高程系统，正确的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","国际统一的坐标系统和高程系统",false,{"key":16,"text":17,"correct":14},"B","国家统一的坐标系统和高程系统",{"key":19,"text":20,"correct":21},"C","城市统一的坐标系统和高程系统",true,{"key":23,"text":24,"correct":14},"D","国家统一的坐标系统和城市统一的高程系统","《城市工程管线综合规划规范》第2.1.2条规定，工程管线的平面位置和竖向位室均应采用城市统一的坐标系统和高程系统。",{"id":6,"name":27,"category":28,"favorite":29},"设计前期与场地设计","建筑工程",0]