[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-922553":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},922553,596,1,"单选题","根据各类工程管线埋设的行垂直排序要求，以下管线中埋在最上面的管线是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","电力管线",true,{"key":16,"text":17,"correct":18},"B","热力管线",false,{"key":20,"text":21,"correct":18},"C","给水管线",{"key":23,"text":24,"correct":18},"D","电信管线","《城市工程管线综合规划规范》第2.2.3条规定，工程管线在道路下面的规划位置宜相对固定，布置次序宜为：电力电缆、电信电缆、燃气配气、给水配水、热力干线、燃气输气、给水输水、雨水排水、污水排水；第2.2.4条规定，工程管线在庭院内建筑线向外方向平行布置的次序，应根据工程管线的性质和埋设深度确定，其布置次序宜为：电力、电信、污水排水、燃气、给水、热力。",{"id":6,"name":27,"category":28,"favorite":29},"设计前期与场地设计","建筑工程",0]