[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-922428":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},922428,596,1,"单选题","以下不属于新建项目土方工程施工前应进行的工作是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采取措施，防止基坑底部土的隆起并避免危害周边环境",true,{"key":16,"text":17,"correct":18},"B","消除基底的垃圾、树根等杂物",false,{"key":20,"text":21,"correct":18},"C","地面排水和降低地下水位工作",{"key":23,"text":24,"correct":18},"D","进行挖、填方的平衡计算，减少重复挖运","《建筑地基基础工程施工验收规范》(GB50202—2002)第6.1.2条中规定：当土方工程挖方较深时，施工单位应采取措施，防止基坑底部土的隆起并避免危害周边环境，此工作属于施工过程中的内容。",{"id":6,"name":27,"category":28,"favorite":29},"设计前期与场地设计","建筑工程",0]