[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-922097":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},922097,595,1,"单选题","建筑物处于规划设计阶段时，不能用于热负荷估算的方法是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","稳定传热法",true,{"key":16,"text":17,"correct":18},"B","概算指标法",false,{"key":20,"text":21,"correct":18},"C","体积热指标法",{"key":23,"text":24,"correct":18},"D","面积热指标法","建筑物处于规划设计阶段时，概算指标法、体积热指标法、面积热指标法可用于对建筑热负荷的估算。",{"id":6,"name":27,"category":28,"favorite":7},"建筑结构与设备","建筑工程"]