[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-921569":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},921569,595,1,"单选题","下列抗震设防烈度为7度的砌体房屋墙与构造柱的施工顺序( )正确。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先砌墙后浇柱",true,{"key":16,"text":17,"correct":18},"B","先浇柱后砌墙",false,{"key":20,"text":21,"correct":18},"C","墙柱同时施工",{"key":23,"text":24,"correct":18},"D","墙柱施工无先后顺序","砌体房屋墙与构造柱的施工顺序应先砌墙后浇柱，留马牙槎并设拉接筋。",{"id":6,"name":27,"category":28,"favorite":7},"建筑结构与设备","建筑工程"]