[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-918536":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},918536,592,1,"单选题","建设单位在竣工验收后（ ）个月内向城乡规划主管部门报送有关竣工验收资料。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":14},"C","5",{"key":22,"text":23,"correct":24},"D","6",true,"熟悉建设工程管理的相关内容。即城乡规划主管部门在建设工程完工后需按照国务院规定对建设工程是否符合规划条件予以核实。未经核实或者经核实不符合规划条件的，建设单位不得组织竣工验收。建设单位在竣工验收后六个月内向城乡规划主管部门报送有关竣工验收资料。",{"id":6,"name":27,"category":28,"favorite":29},"城乡规划原理","建筑工程",0]