[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-918216":3},{"question":4,"library":33},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":31,"analysis":32},918216,591,2,"多选题","在控制性详细规划阶段。编制用地竖向工程规划的工作内容与深度不包括以下选项中的( )项。",[11,15,18,22,25,28],{"key":12,"text":13,"correct":14},"A","确定防洪(潮、浪)堤坝及堤内地面最低控制标高",true,{"key":16,"text":17,"correct":14},"B","确定主、次道路交叉点、转折点的控制标高",{"key":19,"text":20,"correct":21},"C","确定主、次、支三级道路范围全部地块的排水方向",false,{"key":23,"text":24,"correct":14},"D","确定建筑室外地坪规划控制标高",{"key":26,"text":27,"correct":14},"E","落实防洪、排涝工程设施的位置、规模及控制标高",{"key":29,"text":30,"correct":21},"F","补充与调整其他用地控制标高","ABDE","上述选项中的A属于总体规划阶段，用于竖向工程规划的内容;上述选项中的的F、H属于修建性详细规划阶段的竖向工程规划内容",{"id":6,"name":34,"category":35,"favorite":36},"城乡规划相关知识","建筑工程",0]