[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-918072":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},918072,591,1,"单选题","下列关于城市工程管线综合规划的表述，哪项是错误的？（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","在交通十分繁忙的重要地区可以采用综合管沟将工程管线集中敷设",false,{"key":16,"text":17,"correct":14},"B","通常情况下压力管线应避让重力流管线",{"key":19,"text":20,"correct":21},"C","管线覆土深度指地面到管内底（内壁）的距离",true,{"key":23,"text":24,"correct":14},"D","规划内容包括确定各种管线之间的水平净距和垂直净距","避让原则： ①压力管让自流管； ②管径小的让管径大的； ③易弯曲的让不易弯曲的； ④临时性的让永久性的； ⑤工程量小的让工程量大的； ⑥新建的让现有的； ⑦检修次数少的、方便的，让检修次数多的，不方便的。 综合术语： 埋设深度：地面到管道底（内壁）的距离，即地面标高减去管底标高。 覆土深度：地面到管道顶（外壁）的距离。",{"id":6,"name":27,"category":28,"favorite":29},"城乡规划相关知识","建筑工程",0]