[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-917236":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},917236,591,1,"单选题","城市轨道交通建设中，换乘车站应做好规划设计，换乘距离为( )，换乘时间为( )，并结合工程实施条件，选择便捷的换乘方式。换乘通道应满足正常通过和紧急疏散能力。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不宜大于500m;不宜大于10min",false,{"key":16,"text":17,"correct":14},"B","不宜大于350m;不宜大于8min",{"key":19,"text":20,"correct":21},"C","不宜大于250m;不宜大于5min",true,{"key":23,"text":24,"correct":14},"D","不宜大于200m;不宜大于4min","城市轨道交通车站布局过程中，换乘车站应做好规划设计，换乘距离不宜大于250m，换乘时间不宜大于5min，并结合工程实施条件，选择便捷的换乘方式，换乘通道应满足正常通过和紧急疏散能力。",{"id":6,"name":27,"category":28,"favorite":29},"城乡规划相关知识","建筑工程",0]