[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-917034":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},917034,590,2,"多选题","临时建设和临时用地规划管理的首要任务就是依申请合理安排临时建设和临时用地，使其对( )的实施不构成影响，既有利于临时建设和临时用地的需要，又能够保证城乡规划的顺利实施。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","总体规划",false,{"key":16,"text":17,"correct":18},"B","近期建设规划",true,{"key":20,"text":21,"correct":18},"C","控制性详细规划",{"key":23,"text":24,"correct":18},"D","修建性详细规划",{"key":26,"text":27,"correct":14},"E","土地利用总体规划","BCD","",{"id":6,"name":31,"category":32,"favorite":33},"城乡规划管理与法规","建筑工程",0]