[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-916729":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},916729,590,1,"单选题","城市规划编制单位更名时，应当在批准之日起( )内到发证部门办理《资质证书》变更手续。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","15日",false,{"key":16,"text":17,"correct":14},"B","20日",{"key":19,"text":20,"correct":14},"C","25日",{"key":22,"text":23,"correct":24},"D","30日",true,"",{"id":6,"name":27,"category":28,"favorite":29},"城乡规划管理与法规","建筑工程",0]