[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-916006":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},916006,589,2,"多选题","按照现行的《1∶5000、1∶10000、1∶25000海岸带地形图测绘规范》规定，进行水深测量时，在下列（ ）情况下应进行补测。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","测深线间隔超过规定间隔的1\u002F3",false,{"key":16,"text":17,"correct":18},"B","两定位点间测深线漏测",true,{"key":20,"text":21,"correct":14},"C","测深仪回波信号记录中断在图上超过5mm",{"key":23,"text":24,"correct":14},"D","能正确勾绘等深线但海底地貌探测不完善",{"key":26,"text":27,"correct":18},"E","测深期间，验潮中断","BE","进行水深测量时，需要进行补测的情况有：①在一般海区测深仪回波模拟信号或数字记录信号，以及两定位点间测深线漏测在定位图上超过3mm时，在地貌复杂海区发生漏测现象时；②记录式测深仪的零信号或回波信号不正常，不能正确量取水深时；③不能正确勾绘等深线和海底地貌探测不完善时；④验潮工作时间不符合要求时；⑤测深线间隔超过规定间隔二分之一时。",{"id":6,"name":31,"category":32,"favorite":33},"测绘综合能力","建筑工程",0]