[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-915883":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},915883,589,2,"多选题","地图设计文件附录不包括()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","制图区域图幅接合表",false,{"key":16,"text":17,"correct":14},"B","行政区划略图",{"key":19,"text":20,"correct":21},"C","编制经费预算表",true,{"key":23,"text":24,"correct":21},"D","制作进度计划",{"key":26,"text":27,"correct":14},"E","新旧图式符号对照表","CD","地图设计文件附录包括：附表、制图区域图幅接合表、基本资料略图、行政区划略图、整饰样图、设计样图、新旧图式符号对照表、相邻图幅接边关系、相关的样图以及不能用文字清晰、形象地表达其内容和要求时所增加的图纸设计等内容。选项A、B、E是地图设计文件附录的内容。故选CD。",{"id":6,"name":31,"category":32,"favorite":33},"测绘综合能力","建筑工程",0]