[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-915635":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},915635,589,2,"多选题","根据界线测绘内容，界线测绘成果应该包括()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","界桩登记表",true,{"key":16,"text":17,"correct":14},"B","界桩成果表",{"key":19,"text":20,"correct":14},"C","边界点位置和边界走向说明",{"key":22,"text":23,"correct":24},"D","坐标系统以及坐标值",false,{"key":26,"text":27,"correct":14},"E","边界协议书附图","ABCE","根据界线测绘内容，界线测绘成果应该包括：界桩登记表、界桩成果表、边界点成果表、边界点位置和边界走向说明、边界协议书附图。",{"id":6,"name":31,"category":32,"favorite":33},"测绘综合能力","建筑工程",0]