[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-915563":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},915563,589,2,"多选题","对于精密工程控制网布设，以下描述正确的是()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","控制网的精度指标是根据精密工程关键部位竣工位置的容许误差确定的",true,{"key":16,"text":17,"correct":18},"B","精密工程控制网必须要分两次布网",false,{"key":20,"text":21,"correct":14},"C","精密工程控制网必须进行优化设计",{"key":23,"text":24,"correct":14},"D","精密水平控制网通常布设为固定基准下的独立网",{"key":26,"text":27,"correct":18},"E","精密高程控制网主要采用三角高程测量的方法建立","ACD","精密工程控制网布设的要求有：①精密工程控制网一般一次布网；②控制网的精度指标是根据精密工程关键部位竣工位置的容许误差确定的；③精密工程控制网必须进行优化设计；④精密水平控制网通常布设为固定基准下的独立网；⑤精密高程控制网主要采用水准测量的方法建立。选项B、E的描述不正确。故选ACD。",{"id":6,"name":31,"category":32,"favorite":33},"测绘综合能力","建筑工程",0]