[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-915559":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},915559,589,2,"多选题","工程控制网建立的步骤是()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","布设和观测方案设计",true,{"key":16,"text":17,"correct":14},"B","选点埋石",{"key":19,"text":20,"correct":14},"C","观测",{"key":22,"text":23,"correct":14},"D","平差计算",{"key":25,"text":26,"correct":27},"E","项目验收",false,"ABCD","工程控制网建立的过程为设计、选点埋石、观测和平差计算。",{"id":6,"name":31,"category":32,"favorite":33},"测绘综合能力","建筑工程",0]