[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-915558":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},915558,589,2,"多选题","工程测量控制网优化设计的解析法中，可以用于一类设计中的最佳点位的方法是()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","S-变换法",false,{"key":16,"text":17,"correct":18},"B","变量轮换法",true,{"key":20,"text":21,"correct":14},"C","数学规划法",{"key":23,"text":24,"correct":18},"D","梯度法",{"key":26,"text":27,"correct":14},"E","试验修正法","BD","本题考查工程测量控制网优化设计的方法。工程测量控制网优化设计有解析法和模拟法（试验修正法）两种。解析法中，零类设计采用S-变换法；一类设计中的最佳点位确定常采用变星轮换法、梯度法等；二类和三类设计主要采用数学规划法。",{"id":6,"name":31,"category":32,"favorite":33},"测绘综合能力","建筑工程",0]