[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-915548":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},915548,589,2,"多选题","工程施工建设阶段的测量工作主要分为()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","勘察测量",false,{"key":16,"text":17,"correct":18},"B","施工测量",true,{"key":20,"text":21,"correct":18},"C","监理测量",{"key":23,"text":24,"correct":14},"D","验收测量",{"key":26,"text":27,"correct":14},"E","变形监测","BC","工程施工建设阶段测量工作主要分为两个部分：施工测量、监理测量。施工测量的主要内容为：施工控制网的建立、施工放样；监理测量的工作主要为：检查测量、审核施工测量数据。故选BC。",{"id":6,"name":31,"category":32,"favorite":33},"测绘综合能力","建筑工程",0]