[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-915528":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},915528,589,2,"多选题","图根平面控制点的布设，可采用()方法。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","三角高程",false,{"key":16,"text":17,"correct":18},"B","图根导线",true,{"key":20,"text":21,"correct":18},"C","交会测量",{"key":23,"text":24,"correct":18},"D","GPSRTK",{"key":26,"text":27,"correct":18},"E","图根三角","BCDE","图根平面控制点的布设，可采用以下方法：①图根导线；②图根三角；③交会测量；④GPSRTK测量等。A选项（三角高程测量）属于高程控制测量范畴，不属于平面控制测量范畴。故选BCDE。",{"id":6,"name":31,"category":32,"favorite":33},"测绘综合能力","建筑工程",0]